Infrastructure
Engineering and utilities
Roads
32.8 km of new road: riverside roads and internal roads of the area — UZS 1,333.5 billion.
Project cost: UZS 1,333.5 billion. New roads to be built: 32.8 km. Funding source: network company funds (not yet financed, work has not started).
Stage 1 — UZS 160.0 billion: building the riverside roads of the area, 7.0 km.
Stage 2 — UZS 1,173.5 billion: building the internal roads of the area, 25.8 km.
In 2024, a temporary 5.3 km gravel road was built along the Karadarya River.